How can trustees compare proposals for the same works fairly?

Fair comparison starts before the prices arrive: make every provider answer the same scope, assumptions, access plan and completion test.

Solar panels on carport roofs over a row of parking bays

Key takeaways

  • Make providers price the same defined outcome before comparing commercial figures.
  • Read exclusions and assumptions as carefully as the total price.
  • Record why the selected proposal best fits risk, evidence and scheme priorities.

A proposal comparison is only fair when the providers have been asked to solve the same problem. Trustees should read the scope first, then compare inclusions, exclusions, assumptions, programme, access, quality checks and handover. A single total cannot tell the scheme whether one contractor has priced a complete job and another has priced only the visible repair. Dev 360 One can arrange a comparison structure and coordinate questions, but the scheme chooses the appointment and pays the appointed specialist.

Freeze the question before reading price

Before opening the commercial pages, write the outcome at the top of the comparison sheet. For a roof project, it might be stop identified water entry, protect occupied areas, test the completed work and provide maintenance records. For metering, it might be establish unit-level consumption, reconcile readings and price options after evidence is collected. A proposal that solves a different outcome should not win because its total is smaller.

A scheme can issue one clarification to all providers when the scope is ambiguous. Do not privately explain the real requirement to one bidder and leave the others with the original wording. Equal information is part of fair comparison.

Read the programme as a price item. A proposal that finishes quickly may require more access windows, larger crews or temporary services. Another may reduce disruption but keep protection in place longer. Both can be sensible. The comparison should show the trade-off and the effect on residents, maintenance and other projects.

Build a like-for-like comparison sheet

Use columns for work package, quantity or area, preparation, access, materials, labour, testing, reinstatement, waste, programme, assumptions and handover. Put a separate line for exclusions and provisional items. This structure exposes the parts of a job that totals conceal.

Imagine three proposals to repair a boundary wall. The first includes crack repair but not painting. The second includes painting but assumes the wall is dry. The third includes access equipment but excludes removal of unstable sections. None is directly comparable until those conditions are made visible. The scheme can then request a clarified response or split the work into defined packages.

Check whether the proposed quantities came from the same information. If one provider measured on site and another relied on photographs, explain that difference before comparing totals. Ask each provider to identify quantities it has verified and those it has estimated. This gives the scheme a clearer route for clarifying uncertainty.

Interrogate exclusions and assumptions

Exclusions are not bad. Hidden exclusions are dangerous. Ask what the provider expects the scheme, another contractor or the resident to supply. Check scaffolding, traffic control, lifting, isolation, protection, permits, testing, temporary works, security, disposal and making good. Ask what happens if concealed damage is found and who can authorise further investigation.

One proposal may assume weekday access to every unit while another includes evening appointments. One may allow two return visits while another charges for each failed access. These are programme and cost risks, not small administrative details. Record them beside the price so decision-makers see the complete offer.

The decision note should not pretend that every criterion has equal weight. State the priorities for this job: safety, technical fit, occupied-site access, warranty, programme or record quality. Then explain where the preferred response performs better and where a residual risk remains. Trustees can approve a known trade-off; they cannot approve one hidden in a total.

Compare capability and delivery controls

A proposal should show who will perform the work, how supervision will operate, what sequence is planned and how the provider will protect people and common property. Check relevant evidence of previous work, capacity for the proposed period, insurance information where required, conflicts and the named contact. The cheapest paper scope is not useful if the provider cannot mobilise when the scheme needs it.

For a live scheme, ask how deliveries, noise, dust, parking, unit access and emergency call-outs will be managed. A programme that ignores residents creates delays that do not appear in the initial price. The comparison should include communication and escalation, not only materials.

Keep unsuccessful proposals with the comparison. They may contain useful alternatives or evidence for a future phase, but they should not be mixed with the appointed scope. Date each clarification so a later reader knows which assumptions were current when the decision was made.

Assess quality and handover before selection

Write the completion test into the comparison. What inspection, test, photograph, certificate, warranty or maintenance instruction must be supplied? Who reviews it and when? If a proposal says complete on installation, ask how the scheme will know that the intended outcome has been met.

A waterproofing package might require a defined test, photographs of preparation, product information and a list of areas not treated. A plant replacement might require commissioning records, operating instructions and training for the relevant person. Handover is part of the work, not an optional folder added after payment.

Record the reasoned decision

A sound decision note states the scope used, proposals received, clarifications issued, material differences, risk items, preferred route and approval required. It can say that a proposal was not selected because its exclusion made the outcome uncertain, not because the provider was unsuitable in every respect. This is clearer for trustees, owners and the managing agent's file.

This week: take one pending project and create a comparison sheet with eight headings: scope, preparation, access, programme, exclusions, variations, quality and handover. Fill it from the proposals already held. The gaps will show whether the scheme needs clarification before choosing anyone.

What you get

What you get from Dev 360 One

A comparison sheet
Scope, price components, assumptions, exclusions, programme, risk and handover requirements shown side by side.
Clarification questions
A controlled list issued consistently so every provider responds to the same unresolved point.
A decision brief
Material differences and the recommended route explained for trustee and managing-agent review.
An appointment handover
The selected scope, responsibilities, reporting route and open commercial items carried into delivery.
Discuss a scheme challenge

Questions

Should trustees choose the lowest proposal?

Not automatically. Choose the proposal that best meets the defined outcome at an acceptable risk after exclusions, assumptions, access, quality and handover are compared. A lower total that omits preparation or testing may cost more to complete properly.

Can providers submit different methods?

Yes, if the scope states the required outcome and asks providers to describe their method. Record where methods change risk, programme, maintenance or handover. Do not treat materially different outcomes as comparable totals.

How should clarifications be handled?

Send material clarifications to every provider still being considered and keep the responses with the proposals. The comparison sheet should show the question, answer, date and effect on scope or price.